Step 1

Setup

We set up the pre-assembled mould, together with the picked inserts, on a vibrating table.

Step 2

Pouring the mineral compound

At room temperature, we pour our epoxy-mineral compound EPOROC® into the prepared mould. This is done under continuous vibration to compact and de-aerate the material.

Step 3

Curing

Depending on the formulation and the system selected, the mineral casting now cures for between 2 and 24 hours.

Step 4

Demoulding

This is followed by dismantling the mould and demoulding the component.

Step 5

Final assembly + bonding and quality control

After demoulding, we mount linear guides and add-on parts where required. For larger projects, we bond several individually cast and pre-assembled mineral casting components together – rigidly and precisely measured in all axes. Finally, each component undergoes final inspection according to the inspection plan.

Step 6

Delivery

We deliver the finished component by truck to a satisfied customer.